a. Recycling coal combustion by-products
Flyash recycling was 205,000 tons (95 % of flyash produced ) in FY 1995
compared to a projected 226,000 tons (90%) in FY2000. Demand exceeded our
supply of flyash and we could have recycled 226,000 tons in 1995 had it
been available. This program will save our rate payers between 1.6 and
1.7 million dollars in FY95.
b. Wind Power Project
Me Wind Power Project came on line on August 31, 1995 almost a year
ahead of the Summer 1996 projected startup date, It is now estimated that
LCRA will receive 93 GWH/year from this project, up from a projected 90
GWH/year. Through January, 1996, LCRA had received 26 GWH, resulting in
the reduction of 21,000 tons of C02 emissions.
The Wind Power Project is presently at 35 MW and, although we have no
immediate expansion plans, our joint development agreement calls for the
ultimate expansion to 250 MW.
c. DSM Programs
Cumulative total of C02 emissions reductions through FY95 was 72,000
tons, compared to the estimate of 65,000 tons.
d. Supply-Side efficiency improvements
These include a multitude of ongoing programs in generation and transmission.
Completed projects include advanced operator training, maintenance awareness
training, performance testing and analysis and the installation of on-line
controllable loss monitors. Installation of adjustable seals is almost
complete and the installation of additional oxygen probes in the boilers
is about two thirds complete. On-going programs include a capacity maximization
effort and major equipment performance tests. New programs include feedwater
heater replacement and replacement of air pre-heater baskets. The most
significant new program is the replacement of the control systems at the
generation plants. This is a multi-year multimillion dollar project that
is about one-complete and at completion it should result in an efficiency
improvement of about 0.5%.